⚠ ⚠ Top risk: Mechanical Seal Leak · RPN 144 (Critical) — watch this one first at the equipment
Risk Board (all 14 · by RPN · top 6 highlighted urgent)
Shield: Safety = people/environment Production = production only
Technical mechanism/mitigation body in Chinese (red line: no fabricated MT; EN UI labels translated)
14Failure Modes
14High/Critical
9Standards
1Real Accidents
Tap any failure mode to flip to its on-site guidance
Device-level standard/accident index (9 standards / 1 accidents)
Standards (9 de-duplicated)
API 682API 677ISO 21940ISO 10441API 614ISO 10816API 541IEC 61800-5-1IEC 61800-3
Accident Lessons (1 de-duplicated)
CSB-GIVAUDAN-LOUISVILLE-2024csb2024 ↗Givaudan Sense Colour 粉尘爆炸
FM Traceability Cards (14)
Mechanical Seal LeakRPN 144 · Critical
Failure Mechanism
密封面磨损/弹簧失效致工艺介质外泄
How to Detect
Online monitoring · Detection rate 80% ;Re-inspect ≤every12months
Mitigation (What to Do)
RCM Strategy
CBMOn-Condition Maintenance
Interval: High risk 1-3 mo / Medium 6-12 mo / Low risk at turnaround (by API 581 RBI risk ranking)
Engineering-inferred (not measured history); confirm with equipment owner before execution
Standards (1)
Lessons Learned (1)
CSB-GIVAUDAN-LOUISVILLE-2024csb2024Fatalities 2 · SafetyGivaudan Sense Colour 粉尘爆炸Root cause: 可燃粉尘防爆(NFPA 652/654)执行缺陷;设备清洗/维护作业粉尘管控与点火源隔离不足Official source ↗
齿轮箱轴承失效RPN 120 · Critical
Failure Mechanism
齿轮箱轴承疲劳/润滑不良致卡滞或碎裂
How to Detect
Online monitoring · Detection rate 80% ;Re-inspect ≤every12months
Mitigation (What to Do)
- 齿轮箱油样分析
- Vibration monitoring
RCM Strategy
CBMOn-Condition Maintenance
Interval: High risk 1-3 mo / Medium 6-12 mo / Low risk at turnaround (by API 581 RBI risk ranking)
Engineering-inferred (not measured history); confirm with equipment owner before execution
Standards (2)
Lessons Learned (1)
CSB-GIVAUDAN-LOUISVILLE-2024csb2024Fatalities 2 · SafetyGivaudan Sense Colour 粉尘爆炸Root cause: 可燃粉尘防爆(NFPA 652/654)执行缺陷;设备清洗/维护作业粉尘管控与点火源隔离不足Official source ↗
振动高(底座松动/不对中)RPN 90 · High
Failure Mechanism
地脚螺栓松动/不对中致整机振动超标
How to Detect
Online monitoring · Detection rate 80% ;Re-inspect ≤every24months
Mitigation (What to Do)
RCM Strategy
CBMOn-Condition Maintenance
Interval: High risk 1-3 mo / Medium 6-12 mo / Low risk at turnaround (by API 581 RBI risk ranking)
Engineering-inferred (not measured history); confirm with equipment owner before execution
Standards (1)
Lessons Learned (1)
CSB-GIVAUDAN-LOUISVILLE-2024csb2024Fatalities 2 · SafetyGivaudan Sense Colour 粉尘爆炸Root cause: 可燃粉尘防爆(NFPA 652/654)执行缺陷;设备清洗/维护作业粉尘管控与点火源隔离不足Official source ↗